KARACHI: A power breakdown at the Dabeji pump station on Monday, August 25, 2025, has sparked a Karachi water shortage, halting operations at key pumps and threatening supply to millions. The Karachi Water and Sewerage Corporation (KWSC) reported the outage at 6:35 AM, affecting line number 5 in the second phase and shutting down two pumps. This disruption endangers a 100 million gallons per day (MGD) shortfall, impacting East and Central districts including Nazimabad, New Karachi, Landhi, and Korangi. Repairs continue, with full restoration pending.
The incident underscores vulnerabilities in Karachi’s water infrastructure, where dependence on consistent electricity amplifies risks for urban populations. In South Asia’s bustling megacities, such breakdowns highlight broader challenges of rapid urbanisation, climate pressures, and ageing systems. Karachi, home to over 16 million, relies on Dabeji for nearly half its water needs, making any halt a catalyst for public health concerns, economic strain, and social unrest. Repeated failures erode trust in utilities and strain regional resources, mirroring issues in Mumbai and Dhaka where power-water interlinks fuel crises.
KWSC Dabeji Pump Shutdown Water Crisis
The KWSC Dabeji pumps shutdown water crisis stems from a fault in the electrical line, a recurring issue at the facility. KWSC spokesperson Sethi confirmed the breakdown affected critical infrastructure. “We are undertaking repair work on an emergency basis,” Sethi stated. “The system will return to routine operations once the line is fixed. Our teams are mobilised to minimise downtime.”
Dabeji, Karachi’s primary intake point from the Indus River, pumps 380 MGD under normal conditions. The shutdown reduces output by 100 MGD, forcing reliance on auxiliary sources like Hub Dam and groundwater. Residents in affected areas face immediate rationing. Tanker supplies, already overburdened, report bookings exceeding quotas by 30 per cent. One resident in Landhi noted low pressure since morning, compelling families to store water preemptively.
Historical data reveals a pattern. In January 2025, a similar power outage burst two pipelines, causing a 100 MGD deficit. Late June 2025 saw three days without electricity, slashing supply by 350 MGD. Last month, maintenance sidelined one pump, while the North East station endured a separate blackout. These events, linked to poor maintenance and technical glitches over a decade, have cost the city PKR 500 million in emergency measures annually, per KWSC estimates.
Engineers attribute 70 per cent of disruptions to power inconsistencies from K-Electric. Backup generators exist but cover only 20 per cent capacity during peaks. The KWSC urges conservation, advising 50 litres per person daily against the ideal 150 litres.
Karachi Areas Water Supply Disruption Power Outage
The Karachi areas water supply disruption power outage extends beyond Dabeji’s immediate radius. East district towns like Shah Faisal and Malir report 40 per cent reduced flow by noon. Central zones, including Liaquatabad, see intermittent supply, with high-rises relying on boosters. Korangi industrial units halt operations, idling 5,000 workers and risking PKR 10 million in daily losses.
Field reports indicate 200,000 households directly hit, equating to 1 million people. Schools in New Karachi dismissed early, while hospitals stockpile reserves. The outage, lasting over 10 hours, exceeds the average two-hour downtime, per internal KWSC logs. Power restoration hinges on cable splicing, a process vulnerable to weather.
Community leaders call for alternatives. The Muttahida Qaumi Movement (MQM) flagged the issue in assembly, demanding federal intervention. Water theft along distribution lines worsens the scarcity, siphoning 15 per cent en route.
Sindh Govt Response Karachi Water Shortage
The Sindh govt response Karachi water shortage focuses on short-term aid and long-term fixes. Chief Minister Murad Ali Shah directed PKR 100 million for tanker deployment on August 2, 2025, amid rising complaints. “Our government prioritises resolving Karachi’s water crisis through sustained projects,” Shah said during a press briefing. This includes augmenting Hub Dam supply from 100 MGD to 200 MGD, pending federal nod.
Local Government Minister Saeed Ghani announced 500 additional tankers for affected zones. “We coordinate with KWSC to bridge the gap during outages,” Ghani added. The response builds on K-IV project progress, targeting 260 MGD by 2026 via new pipelines. Yet, critics note delays, with only 40 per cent completion by August 2025.
Federal involvement remains limited, though Energy Minister Awais Leghari pledged grid upgrades.
Background: Recurring Dabeji Vulnerabilities
Dabeji’s woes trace to its 1990s commissioning, when capacity matched 10 million residents. Today, demand outstrips by 400 MGD. A 2024 audit flagged 25 per cent equipment obsolescence. Power dependency, without full redundancies, invites chaos. Previous breakdowns, like the 36-hour shutdown on August 11, 2025, due to cable faults, mirror Monday’s event. These cost health epidemics, with cholera cases up 20 per cent post-outages.
International donors, including the World Bank, fund PKR 20 billion in reforms, emphasising solar backups. KWSC trains 200 staff yearly on crisis management, yet implementation lags.
What’s Next: Averting Future Crises
Repairs at Dabeji target completion by Tuesday, August 26, restoring 80 per cent supply. KWSC plans quarterly drills. The Sindh government eyes a PKR 5 billion resilience fund, integrating smart grids. Residents prepare for phased recovery, with alerts via SMS.
The Karachi water shortage Dabeji power breakdown serves as a stark reminder. Without systemic overhauls, such disruptions will persist, testing the city’s endurance.
Published in SouthAsianDesk, November 16th, 2025
Follow SouthAsianDesk on X, Instagram, and Facebook for insights on business and current affairs from across South Asia.