The Punjab land reform project funded by the World Bank has reached 90 percent physical progress ahead of its June 2027 closing date, according to a World Bank document reported by Business Recorder. Punjab has digitised and notified 5,805 of its 6,014 revenue villages, registered about 69.9 million land rights and converted more than 31 million person-based land records into parcel-based records under the project, which the Bank has now upgraded to “Highly Satisfactory” for both development progress and implementation.

How the Punjab Land Reform Project Is Performing

The Punjab Urban Land Systems Enhancement Project, known as PULSE, is being carried out by the Punjab Board of Revenue and the Punjab Land Records Authority (PLRA). It aims to improve land records, clarify ownership and identify public land for development, including housing programmes. The World Bank approved it on 10 March 2022 with a $150 million credit, later revised to $145.76 million.

Several indicators now exceed their end targets. About 69.92 million land rights have been registered or linked with the Land Records Management Information System (LRMIS), against a closing target of 50.68 million. Digital cadastral maps cover 86 percent of Punjab, compared with a target of 61.8 percent, and 31.18 million person-based records have been converted to parcel-based records, against a target of 28 million. The digitisation covers more than 24.4 million landowners.

Women, Joint Holdings and Public Land

The report also tracks who benefits. Women account for 31 percent of registered land rights, marginally below the 32 percent target, while 7.57 million newly registered or updated land records were filed by or jointly with women, against a target of six million. On jointly owned land, 495,163 of 1.747 million eligible holdings have been partitioned, which is 28 percent. That work created about 1.18 million new parcels, including 94,833 registered in women’s names.

On public land, the project has screened 933.5 hectares for housing against a target of 1,000 hectares, and identified 200 public land sites for development programmes, meeting that target. Under the Green Property Certificate initiative, 54,694 certificates have been issued, with 23,280 cases approved and 37,272 field assessments completed.

Where Progress Is Slower

The upgrade does not mean every part of the project is complete. Of the 6,014 revenue villages, 27 have been submitted for notification and work on the remaining 182 is pending. Land records digitisation also remains well ahead of spending. Against the revised credit of $145.76 million, about $90.08 million had been disbursed by October 2026, or 61.8 percent, which leaves $55.68 million undisbursed with about seven months to go. The World Bank kept its overall risk rating at “Moderate”.

An earlier assessment shows that the project has needed adjustments. A mid-term review reported by Business Recorder in 2025 rated implementation “Satisfactory”, but said an indicator on integrating the records of private housing societies would need its end target cut from 4,374 to 2,187, because fewer societies had joined than planned.

Why Land Records Digitisation Matters

Officials have long argued that clear records reduce disputes. Commissioner Rawalpindi Aamir Khattak said in January 2025 that most land revenue court cases involve jointly owned land, where hostilities can continue for years, and that the aim is to move toward single-owner records. The project replaces the older person-based khewat system with parcel-based records linked to maps, so that each parcel and its owner can be identified together.

Independent evidence on how much this reduces litigation was not included in the World Bank document reported by Business Recorder, which measures progress by project outputs such as records registered and maps updated.

What Comes Next

The project must complete all activities by its closing date of 30 June 2027. The main questions are whether the remaining 182 villages can be notified in time, whether the pace of partition of jointly owned holdings can increase, and whether disbursement catches up with physical progress. Whether the digitised records are used and kept current after the project ends will also matter, since the benefits depend on keeping the registry accurate.

For now, the Punjab land reform project is on track by the World Bank’s own assessment, with the strongest results in digital mapping and registration and the slowest in partitioning joint holdings and spending. The final results will be judged on how reliably the new system works for landowners once the project closes.

Follow SouthAsianDesk on X, Instagram and Facebook for insights on business and current affairs from across South Asia.

Leave a Reply

Your email address will not be published.